continue reading hover preload topbar hover preload widget hover preload

Manage the Schedule for Small Projects

April 6 2015

All projects need a schedule. If you have a small project perhaps the schedule is a simple checklist or Excel spreadsheet. As projects get larger they need more formal scheduling templates and tools.

The processes you use to manage a schedule also vary depending on the size of the project. Large projects need a lot of schedule management rigor. Small projects can use a lighter process. The following steps can be used to mage the schedule of a small project.

Review the schedule on a weekly basis.

Identify activities that have been completed during the previous week and update the schedule to show they are finished.

Determine whether there are activities that should be completed, but are not. Work with the individual that is assigned to the work see what is going on. Determine how much additional effort and duration are needed to complete the work and update the schedule accordingly.

Evaluate the remaining work to see if the project will be completed within the original duration. You may find that even though some activities may be completing later than planned, other activities may be completing early and the overall schedule may still be okay.

If your project is trending behind schedule, think of schedule management techniques you can apply to get back on schedule. Raise a schedule risk in your status report if the original deadline appears to be in jeopardy.

Adjust the schedule so that it reflects the remaining work to be completed, and is as accurate as possible.

Since this is a process for a small project, it would be unusual to have major problems with the schedule. The consequences of problems on small projects are generally small as well.

Define the Objectives of Your Project

March 23 2015

Objectives are concrete statements that describe the things the project is trying to achieve. They are included in your Project Charter. An objective should be written in a way…

Four Steps to Show the Value of Training

March 9 2015

Many businesses struggle with whether they are getting their money’s worth in sending employees to training classes. This question can be applied to project management training as well as…

Three Techniques for Scope Change Management

February 23 2015

1. Hold Everyone Accountable for Scope Management

Many scope management processes work well at the project manager level, but get compromised by team members. If the project manager is diligent…

Five Steps Before Estimating Work

February 9 2015

Estimating is hard enough. It is even harder if you are not prepared. Estimating a 20 hour chunk of work is not so hard. Estimating for full projects or…

Understand the Risk Tolerance Level in Your Organization

January 29 2015

All projects have risks and all risks have the potential for negatively impacting the project. You use risk management to determine the risks that are important enough to manage….

The Power of the Aligned Organization

January 12 2015

When was the last time you rode in a car with wheels that were not properly aligned? Chances are it was a pretty rough ride. The car either pulled…

The Customer May Not Know Enough to Completely Define the Project

December 29 2014

Sometimes the project manager places too high an expectation on the amount of foresight and vision that customers and sponsors have. In many cases, the project manager will go…